Cedar Hill Road Revised Schedule 12/03/2019

Revised Schedule Cedar Hill Road Water Main Construction (12/03/19)
Revised Schedule Cedar Hill Road Water Main Construction (12/03/19)

“Revised Schedule -Cedar Hill Road Water Main Construction - Restarting Monday, December 3rd - Expect Delays

The Aquarion Water Company will restart an emergency project to replace a section of temporary water main on Cedar Hill Road from Shady Lane to a point approximate 200 feet east of the intersection on Monday, December 3rd.  The work is being performed by Simscroft-Echo Farms, Inc. of Simsbury, CT.  The completion of the project is expected to continue through December 6th.  Final roadway restoration will be complete in the spring of 2020. The contractor will reduce the traffic to alternating one-way traffic from 7:00am until 3:30pm, Monday through Friday.”

Motorists should expect delays. Motorists are advised to maintain a safe speed when driving in this vicinity.”